Key Spec 7
Client:
Frasers Property
Project Type:
Design and Construct
Completion Date:
January 31, 2019
Sector:
Logistics
Project Features:

Energy Efficiency

Energy Usage Remote Monitoring

Greenstar Compliant

Lighting Control

Lighting Design

Fibre Optic

Wireless Access Points

Key Spec 7

Consisting of a 14,000m2 manufacturing warehouse, the project required the supply and installation of High Voltage reticulation supplying the 1x 2MVA kiosk substation. The installation required 4 sets of 630mm Flexi Aluminium per phase which had to be reticulated over a boiler room and switch room as the mains were required to enter the main switchboard. Further to this underground reticulation was required to service refrigeration, the various distribution boards and bottling lines throughout the facility.